What does it mean to sequence activities?

Step 2: Activity Sequencing involves the accurate identification of constraints/relationships among activities and establishing the order in which the activities will be accomplished. There are several inputs to this step: [1]

Advertisements

  • The activity list developed in the Activity Definition step,
  • The product description and characteristics,
  • Mandatory constraints/dependencies, such as the fact that a prototype must be fabricated before it can be tested,
  • Discretionary constraints/dependencies developed by the program management team based on “best practices” or specific sequences desired by management,
  • External dependencies, such as availability of test sites, and
  • Other constraints and assumptions.

Schedule Preparation

A number of tools and techniques are useful in developing the logic diagrams that reflect the desired activity sequencing. They include various network scheduling techniques that can be used to include: [1]

Advertisements

  • Critical Chain Method (CCM)
  • Critical Path Method (CPM)
  • Precedence Diagram Method (PDM)
  • Program Evaluation and Review Technique (PERT)

There are a number of scheduling software programs available that develop activity sequencing. A few of the popular ones are:

Once the WBS is created, the work packages in it are further decomposed into activities. Activities from different work packages will have to be sequenced in order to progress and complete the project work. This creates logical relationships between the activities also known as network logic, which are of 4 types:

  1. FS – Finish to Start – an activity must finish before the next can start; this is the most common one used.

  2. FF – Finish to Finish – an activity must finish before the next can finish. For example level concrete can finish only when pouring concrete also finishes

  3. SS – Start to Start – an activity must start before next can start. For example, laying of foundation pillars can start only after digging of the foundation has started

  4. SF –Start to Finish - an activity must start before next can finish, this is the rarest and should be avoided. An example is: install of new oil pipeline must start before shutting off the old pipeline can finish

As you can see, the logic will depend on the nature of the work or industry.

The most popular method used for sequencing is the Precedence Network Diagramming method. Activities are connected in such a diagram, thus showing their sequence from the start to finish of the project. Some of them may be sequenced even in parallel or with overlap.

Activities have dependencies which are of 4 types

  1. Mandatory (hard logic) – this is due to the nature of work or a compliance requirement

  2. Optional or discretionary (preferred or soft logic) – this is due to best practice or desire. For example, doing the plumbing and electrical work separately even though it can be done in parallel. Removal of such dependencies usually saves time.

  3. External – for example, waiting for a supplier to send raw materials

  4. Internal – for example, waiting for a project team member to complete the design before it can be given to someone for review

Lean Six Sigma Green Belt Course Agile Class Six Sigma Yellow Belt Certification Online ITIL Foundation Course Lean Six Sigma Black Belt Certification Exam

PMP Boot Camp Portland PMP Boot Camp Philadelphia PMP Boot Camp Washington DC PMP Training Manila PMP Training Lagos

PMP Home

What is PMP? Benefits of PMP Certification Get PMP Certified Eligibility criteria for PMP exam PMI Membership Benefits How to Prepare for PMP Exam Cost of PMP Certification PMP Exam Fee PMP Exam Questions Type of questions you can expect in the PMP exam How to Practice for the PMP Exam Applying for the PMP Exam Day of Exam Maintaining your PMP Certification PMI PDUs - Under new PMP Talent Triangle® How to Claim PDU’s Career Opportunities for PMP Certified Professionals About the PMP ® Credential

Introduction to Project Management

Basic Concepts of Project Management Project Lifecycle and Tailoring Project Business Documents

The Project Environment

Organizational Structure Other Influences on Project Management The PMO

Role of the Project Manager

Project Manager Role and Sphere of Influence PMI Talent Triangle The PM as an Integrator

Integration Management

Integration Management Overview Project Charter Project Charter-Business Case Project Charter-Project Selection Constraints and Assumptions Project Statement of Work (SOW) Develop Project Management Plans Project Documents Monitor and Control Project Work Perform Integrated Change Control Managing Project Knowledge Closing a Project or Phase

Scope Management

Balancing Stakeholder Requirements Scope Management Overview Scope Management Plan Scope Management Process Project Scope Statement

Schedule Management

Schedule Management Overview Schedule Management Plan Introduction on Estimation Schedule Network Analysis Sequencing Activities

Cost Management

Cost Management Overview Earned Value Measurement How is estimation done?

Quality Management

Quality Management Overview Manage and Control Quality Cost-Benefit Analysis

Resource Management

Resource Management Overview Resource Management Plan Team Building Powers of Project Manager Control Resources

Communication Management

Communication Management Overview Communication Management Plan Manage and Monitor Communications Plan Communications

Risk Mangement

Risk Management Overview Risk Management Plan Risk Identification and Analysis Plan Risk Responses Implement and Monitor Risks

Procurement Management

Procurement Management Overview Procurement Management Process Procurement Statement Of Work Noncompetitive Forms Of Procurement What is a Contract? Control Procurements Close Procurements

What is sequential activities?

Sequential activities follow a logical order or sequence and involve steps in a working plan. Examples of such activities include writing a message, drawing a recognizable picture, and putting together a puzzle.

Why is it important to sequence activities in a project?

Sequencing tasks is an important part of project task management because it helps you make the most out of your resources and help you identify critical tasks and prioritize them.

What is sequencing in early childhood?

Sequencing is the ability to arrange language, thoughts, information, and actions in a certain order. The ability to sequence depends heavily on the development of executive functioning skills like attention, organization, planning, and working memory.

What does out of sequence activity mean?

Quick Answer: an out-of-sequence activity is any activity that is in-progress or has completed before one or more of its predecessors. This condition is reported in the warnings section of the P6 Professional and EPPM Schedule Log.