What is the correct formula for manufacturing cycle efficiency MCE ratio?

Unit Converter

Enter the total value-added production time (min) and the total production cycle time (min) into the Manufacturing Cycle Efficiency Calculator. The calculator will evaluate the Manufacturing Cycle Efficiency. 

  • Production Efficiency Calculator
  • Takt Time Calculator
  • Cycle Time Calculator

The following two example problems outline the steps and information needed to calculate the Manufacturing Cycle Efficiency.

MCE = VAT / PCT * 100

Variables:

  • MCE is the Manufacturing Cycle Efficiency (%)
  • VAT is the total value-added production time (min) 
  • PCT is the total production cycle time (min) 

How to Calculate Manufacturing Cycle Efficiency?

The following steps outline how to calculate the Manufacturing Cycle Efficiency.


  1. First, determine the total value-added production time (min). 
  2. Next, determine the total production cycle time (min). 
  3. Next, gather the formula from above = MCE = VAT / PCT * 100.
  4. Finally, calculate the Manufacturing Cycle Efficiency.
  5. After inserting the variables and calculating the result, check your answer with the calculator above.

Example Problem : 

Use the following variables as an example problem to test your knowledge.

total value-added production time (min) = 30

total production cycle time (min) = 75

MCE = VAT / PCT * 100= ?

What is the correct formula for manufacturing cycle efficiency MCE ratio?

45.The formula for computing Manufacturing Cycle Efficiency (MCE) is:a.Processing Time / (Processing Time + Move Time + Inspection Time + Waiting Time +Other non-value added time)b.Theoretical Capacity / Production hours availablec.Cycle time per unit * velocityd.None of the aboveANS: APTS:1OBJ:13-2

46.Cycle time isPTS:1OBJ:13-2

Get answer to your question and much more

47.The number of units that can be produced in a given period of time is calledPTS:1OBJ:13-2

Get answer to your question and much more

48.Delivery performance can be improved byPTS:1OBJ:13-2

Get answer to your question and much more

At the beginning of 2010, Peters Company installed a JIT purchasing and manufacturing system. Thefollowing information has been gathered about one of the company's products:Theoretical annual capacity2,000This edition is intended for use outside of the U.S. only, with content that may be different from the U.S. Edition. This may not be resold,copied, or distributed without the prior consent of the publisher.

Providing an example of how manufacturing cycle efficiency is calculated is one good way to emphasize the importance of process management. In a manufacturing concern, the efficiency of the work processes likewise entails cost accounting efficiency.

Manufacturing can be quite complex as it involves several stages or steps before an item becomes complete. Thus, best practices require proper process management in order to avoid the unnecessary time, space, or resources being consumed by process steps that do not actually add value to the goods being sold.

You may have heard of some start-up manufacturers who tend to encounter difficulties in meeting customers’ orders and thus lose continued patronage of their products. In other cases, competitors are able to offer lower prices that other manufacturers cannot afford because they have to recover a substantial amount of manufacturing costs.

What seems to be the difference between manufacturers who can meet deadlines from those who cannot? What about the manufacturers who can offer a more competitive price than those who have to recover a greater amount of manufacturing costs? We can find out the answers, by determining the manufacture cycle efficiency, calculated in our case study sample.

Knowing how manufacturing cycle efficiency (MCE) is calculated is only a part of a business process management system. Hence, there is also the need to know how to identify what seems to be ailing a particular business, which we will explain briefly by way of example.

Image Credit: B&P Manufacturing Liberator hand truck from Wikimedia Commons

Determining the Components of the MCE

What is the correct formula for manufacturing cycle efficiency MCE ratio?

Keep in mind that each step or process denotes time and resources that are consumed, with the expectation that they can be recovered with a reasonable rate of profit or value added. This profit represents the mark-up that is added to the selling price being offered to customers.

In understanding this, it would be important for the process manager to determine which process steps add value and which do not. These components are called value-added and non-value-added process steps and are defined as follows:

  • Value-Added Process Steps – The work performed within a manufacturing cycle that adds to the function or enhances the form of the product in such a way that it becomes a finished good that is pleasing or attractive to a customer. The latter, then, would be willing to pay additional value aside from the product’s manufacturing cost.

  • Non-Value-Added Process Steps – These steps are the exact opposite of the value-added steps wherein no form or functionality is contributed by the work performed, but they still form part of the manufacturing cost to be recovered and imputed in the selling price that customers have to pay.

Inasmuch as our goal is to determine efficiency, we have to first establish the total time that each manufacturing cycle takes, which is known as the cycle time or throughput time. The cycle time will then be identified as to which process steps are valued-added and which steps are non-valued-added, in order to assign the time-equivalent of these two components.

After determining their respective cycle time values, you can now calculate the manufacturing cycle efficiency.

Image Credit: Algots

The Manufacturing Cycle Efficiency Formula

After knowing the manufacturing cycle time and value-added cycle time, you can now use the manufacturing cycle efficiency formula to determine the MCE rate:

Manufacturing Cycle Efficiency (MCE) = Value-Added time/Manufacturing Cycle Time

The resulting quotients will then be expressed in terms of percentage by multiplying the number derived by 100%.

However, as some would say, it is easier said than done, especially if the process manager is at a loss on how to identify which of the process steps add value or which do not. Hence, we find it necessary to provide further explanations by giving the readers an example of how manufacturing cycle efficiency is calculated.

Read more about the manufacturing cycle efficiency, calculated in a complete example on the next page.

Example of How to Calculate the MCE

What is the correct formula for manufacturing cycle efficiency MCE ratio?

In calculating the MCE, your first concern is to identify the manufacturing processes involved. The best way to organize this is to create a process map. In our example, the work performed in each manufacturing cycle is for a batch of 100 garments assigned to 5 sewers.

  • The process map will help you identify which of the actions performed during the manufacturing cyle add value to the production of 100 garments. Kindly click on the image to get a larger view of the sample process map

  • Jot down the process steps you have mapped out, together with the equivalent number of days or hours to complete each step. In our example, the process steps and their cycle time are as follows:

What is the correct formula for manufacturing cycle efficiency MCE ratio?

(1) Sample Making and (2) Pattern Production = 5 days

(3) Grading (4) Marker Making (5) Spreading = 2 days

(6) Cutting = 2 days

(7) Sorting/Bundling = 1 day

(8) Sewing/Assembling = 1 day

(9) Inspection = 1 day

(10) Pressing = 1 day

(11) Packaging = 1 day

  • We summed up the equivalent number of days to get the manufacture cycle time, wherein we derive a total of 14 days.
  • Classify the value-added time or those actions performed to transform the raw materials into 100 finished garments:

Cutting = 2 days

Sewing and assembling = 1 day

Total Number of Value-Added Days = 3 days

  • Calculate the Manufacturing Cycle Efficiency using the formula: Value-added process time / Manufacturing Cycle Time

MCE = 3 days / 14 x 100%

MCE = 21.42%

Image Credit: Created by author cscantoria.to serve as visual aid for the explanations on MCE calculation

.

Understanding the Significance and Use of the MCE

We have established that for every 100 pieces of garments completed by 5 sewers in 14 days, only 21% of the actions performed add value in order to transform the raw materials into finished goods.

However, this does not mean that the remaining 11 days, which represent the non-value-added process steps, should be dispensed with. They are still considered necessary steps, in order to proceed to the value-added processes and attain completion as finished goods that customers are willing to buy at a value-added price.

What this tool aims to achieve is to identify the processes, for which alternatives or possible solutions could be applied, to lessen the non-value-added time spent in manufacturing a product. The cost accounting department, on the other hand, can come up with a better production cost on which to base the selling price.

To complete the said objective for this analysis, we have also come up with the recommended methods on how to lessen the non-value-added time it takes to complete a manufacturing cycle time in garment manufacturing:

  • The use of CAD (Computer-Aided Design) or CAM (Computer-Aided Manufacturing) equipment in view of the speed, accuracy and ease by which samples, patterns, gradings, and markings can be completed.
  • The establishment of critical points, where pre-inspections should be done before the garment undergoes the finishing process.
  • The use of spreading machines, wherein fabrics spanning over 100 feet are mechanically stacked one on top of another.
  • Other CAM equipment used for cutting, sorting, and bundling.
  • Arranging the floor layout of the production area and the work stations where the flow of work can be done continuously without the need to physically transfer the raw materials-in-process to another work station.

These are only some of the recommendations, which most garment manufacturers have proved as effective and efficient work-process technologies and techniques. The cost of the CAD or CAM equipment will then be capitalized and allocated by way of depreciation, to match their contribution to revenue generation throughout the years of their useful lives.

Take note, however, that the examples of the process cycle time for garment manufacturing provided above are only examples. They should not be misconstrued as the representation of the standards for garment manufacturing process steps and cycle time. They are merely provided for the purpose of illustrating how manufacturing cycle time, calculated, can give emphasis on its significance as a tool for process management and costing.

.

What is the manufacturing cycle efficiency MCE?

Manufacturing cycle efficiency measures the percentage of time that is spent on producing a product through value-added activities. It is used by many businesses so that non-value-added activities could be eliminated, and as a result, the cost could be reduced.

What is the formula for manufacturing cycle time?

Total amount of goods produced/Time of Production = Cycle time.

What does a manufacturing cycle efficiency MCE of less than 1 mean?

An MCE of less than 1 means that the production process includes non-value added time. An MCE of 0.40 means that 40% of throughput time consists of actual processing, while the other 60% consists of moving, inspection, and other non-value-added activities.

What is the service cycle efficiency ratio?

Definition: Cycle Efficiency, often-abbreviated CE, is a ratio that measures the effectiveness and productivity of the production process by comparing the value added time with the total production time. In other words, it's a calculation that cost accountants use to measure how efficiently products are being produced.