Whats the correct order of the time Management planning processes

What is Time Management in Project Management?

Time management is the management of the time spent, and progress made, on project tasks and activities. Excellent time management requires the planning, scheduling, monitoring, and controlling of all project activities. Time management is one of the six major functions of project management, according to the Project Management Institute. When some people refer to project time management, they’re also referring to the tools and techniques used for managing time. 

Why is time management important in project management?

A project, by definition, has an official end date. In order to meet this date, every project needs a schedule and to manage their own time and the team’s time to ensure that the schedule is met. Imagine you decide to renovate a bathroom in your house. You figure you’ll do it in your spare time, so you don’t give yourself an end date or create a project schedule. You also don’t do anything to make sure you regularly have time to work on the renovation.

What happens? If you’re like most people, the answer is that years go by and your ‘project’ never gets finished.

Likely it is faced with constant delays, and you may run into the following issues:

  • You felt too busy to work on it, so you pushed it to the back of your to-do list
  • You didn’t order the new tiles in time and had to wait for them to come in
  • You weren’t able to find a plumber and couldn’t install the sink or toilet after they were delivered
  • You found out too late that inspections need to be booked months in advance
  • And so on

That’s why time management is so critical. Without it, projects won’t get done on time, and may not get done at all.

The seven main processes in project time management

  1. Plan schedule management: Many resources don’t mention this process when discussing time management. But, before you can complete the other steps, you need to plan how you will manage your schedule. Some questions you should answer are: What software or tool will you use? Who will be responsible for using the software? How often will the schedule be reviewed? What controls will be put in place to ensure everyone stays on schedule?
  2. Define activities: Once you have your time management plan, you can identify and define your project activities. Often a work breakdown structure (WBS) is used to help define activities and tasks within a project. Major milestones should also be determined.
  3. Sequence activities: Now that you know all of the tasks that must be completed, you can start sequencing them in the proper order with a network diagram.
  4. Estimate resources: In project management, the term ‘resources’ often refers to people. However, you also need to identify which tools, materials, systems, budget, and other resources you will need for each task to be completed.
  5. Estimate durations: Once you know which tasks must be completed and what you need to accomplish them, it’s time to estimate how long it will take to complete each activity. Some project managers use PERT (Program Evaluation Review Technique) to come up with their durations, especially if there’s a lot of unknown factors at play.
  6. Develop the project schedule: This can be done by inputting your activities, durations, start and end dates, sequencing, and relationships into a scheduling software.
  7. Control the schedule: Once your schedule is created, it needs to be monitored and controlled. Progress needs to be reviewed and updated on a regular basis so you can compare your actual work completed against the plan. This allows you to see if there are areas you’re falling behind schedule.

Further reading:

  • Project Management Basics: 6 Steps to a Foolproof Project Plan
  • How 5 PM Experts Create a Fail-Safe Project Management Plan
  • How to Keep Employees on Track with a Time Management Calendar
  • 4 Tips to Improve Your Time Management this Holiday Season
  • Stress-Free Reporting with Scheduled Report Reminders

0 Exact answers 0 Text answers 256 Multiple-choice answers

You’re managing a project, when your client tells you that an external problem happened, and now you have to meet an earlier deadline. Your supervisor heard that in a situation like this, you can use schedule compression by either crashing or fast-tracking the schedule, but he’s not sure which is which. What do you tell him?

Whats the correct order of the time Management planning processes
Crashing the project adds risk, while fast-tracking adds cost

Whats the correct order of the time Management planning processes
When you crash a project, it always shortens the total duration of the project

Whats the correct order of the time Management planning processes
Crashing the project adds cost, while fast-tracking adds risk

Whats the correct order of the time Management planning processes
When you fast-track a project, it always shortens the total duration of the project


Whats the correct order of the time Management planning processes

You are managing a software project. Your QA manager tells you that you need to plan to have her team start their test planning activity so that it finishes just before testing begins. But other than that, she says it can start as late in the project as necessary. What’s the relationship between the test planning activity and the testing activity?

Whats the correct order of the time Management planning processes
Start-to-Start (SS)

Whats the correct order of the time Management planning processes
Start-to-finish (SF)

Whats the correct order of the time Management planning processes
Finish-to-Start (FS)

Whats the correct order of the time Management planning processes
Finish-to-Finish (FF)


You’re managing an industrial design project. You’ve come up with the complete activity list, created network diagrams, assigned resources to each activity, and estimated their durations. What’s the next thing that you do?

Whats the correct order of the time Management planning processes
Use Rolling Wave Planning to compensate for the fact that you don’t have complete information

Whats the correct order of the time Management planning processes
Create the schedule

Whats the correct order of the time Management planning processes
Consult the project scope statement and perform Sequence Activities

Whats the correct order of the time Management planning processes
Use fast-tracking to reduce the total duration


Which of the following is NOT an input to Develop Schedule?

Whats the correct order of the time Management planning processes
Activity list

Whats the correct order of the time Management planning processes
Project schedule network diagrams

Whats the correct order of the time Management planning processes
Resource calendars

Whats the correct order of the time Management planning processes
Schedule baseline


Three members of your project team want to pad their estimates because they believe there are certain risks that might materialize. What is the BEST way to handle this situation?

Whats the correct order of the time Management planning processes
Estimate the activities honestly, and then use a contingency reserve to cover any unexpected costs

Whats the correct order of the time Management planning processes
Allow more time for the work by adding a buffer to every activity in the schedule

Whats the correct order of the time Management planning processes
Tell the team members not to worry about it, and if the schedule is wrong it’s okay for the project to be late

Whats the correct order of the time Management planning processes
Crash the schedule


Which of the following tools is used for adding buffers to a schedule?

Whats the correct order of the time Management planning processes
Three-point estimates

Whats the correct order of the time Management planning processes
Critical chain method

Whats the correct order of the time Management planning processes
Expert judgment

Whats the correct order of the time Management planning processes
Critical path analysis


Whats the correct order of the time Management planning processes

You’re managing an interior decoration project, when you find out that you need to get it done earlier than originally planned. You decide to fast-track the project. This means:

Whats the correct order of the time Management planning processes
Starting the project sooner and working overtime

Whats the correct order of the time Management planning processes
Assigning more people to the tasks at a greater total cost, especially for activities on the critical path

Whats the correct order of the time Management planning processes
Starting activities earlier and overlapping them more, which will cost more and could add risks

Whats the correct order of the time Management planning processes
Shortening the durations of the activities and asking people to work overtime to accommodate that.


You’re managing a construction project. You’ve decomposed work packages into activities, and your client needs a duration estimate for each activity that you come up with. Which of the following will you use for this?

Whats the correct order of the time Management planning processes
Milestone list

Whats the correct order of the time Management planning processes
Activity list

Whats the correct order of the time Management planning processes
Critical path analysis

Whats the correct order of the time Management planning processes
Project schedule network diagram


What’s the correct order of the Time Management planning processes?

Whats the correct order of the time Management planning processes
Sequence Activities, Define Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule

Whats the correct order of the time Management planning processes
Define Activities, Sequence Activities, Develop Schedule, Estimate Activity Resources, Estimate Activity Durations

Whats the correct order of the time Management planning processes
Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule

Whats the correct order of the time Management planning processes
Develop Schedule, Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations


Which of the following is NOT a tool or technique used in Estimate Activity Durations?

Whats the correct order of the time Management planning processes
SWAG Estimation

Whats the correct order of the time Management planning processes
Parametric Estimation

Whats the correct order of the time Management planning processes
Analogous Estimation

Whats the correct order of the time Management planning processes
Three-Point Estimation


Whats the correct order of the time Management planning processes

You’re managing a project to build a new project management information system. You work with the team to come up with an estimate of 27 weeks. In the best case, this could be shortened by two weeks because you can reuse a previous component. But there’s a risk that a vendor delay could cause the project to be delayed by five weeks. Use PERT to calculate a three-point estimate for this project.

Whats the correct order of the time Management planning processes
25.83 weeks

Whats the correct order of the time Management planning processes
26 weeks

Whats the correct order of the time Management planning processes
27.5 weeks

Whats the correct order of the time Management planning processes
28.3 weeks


You’re managing a software project, when your customer informs you that a schedule change is necessary. Which is the BEST thing to do?

Whats the correct order of the time Management planning processes
Consult the schedule management plan

Whats the correct order of the time Management planning processes
Notify the team and the sponsor that there’s going to be a schedule change

Whats the correct order of the time Management planning processes
Influence the factors that cause change

Whats the correct order of the time Management planning processes
Refuse to make the change because there’s already a schedule baseline


Your company has previously run other projects similar to the one you’re currently managing. What is the BEST way to use that information?

Whats the correct order of the time Management planning processes
Check the organizational process assets for lessons learned and other information about the past projects

Whats the correct order of the time Management planning processes
Use parametric estimation to estimate your project based on past projects’ performance

Whats the correct order of the time Management planning processes
Start from scratch because you don’t want mistakes from past projects to influence you

Whats the correct order of the time Management planning processes
Reuse the project management plan from a past project


You’re planning the schedule for a highway construction project, but the final date you came up with will run into the next budget year. The state comes up with capital from a reserve fund, and now you can increase the budget for your resources. What’s the BEST way to compress the schedule?

Whats the correct order of the time Management planning processes
Go back to your three-point estimates and use the most optimistic ones

Whats the correct order of the time Management planning processes
Use the extra budget to increase your contingency reserve

Whats the correct order of the time Management planning processes
Hire more experts to use expert judgment so your estimates are more accurate

Whats the correct order of the time Management planning processes
Crash the schedule


You’re managing a software project. You’ve created the schedule, and you need to figure out which activities absolutely cannot slip. You’ve done critical path analysis, identifying the critical path and calculating the early start and early finish for each activity. Which activities cannot slip without making the project late?

Whats the correct order of the time Management planning processes
The ones with the biggest difference between ES and LF

Whats the correct order of the time Management planning processes
The activities on the critical path

Whats the correct order of the time Management planning processes
The activity with the most lag

Whats the correct order of the time Management planning processes
The last activity in the project, because it has no float


Whats the correct order of the time Management planning processes

What are the 5 elements of time management?

5 essential time management techniques.
Be intentional: Keep a to-do list. ... .
Be prioritized: Rank your tasks. ... .
Be focused: manage distractions. ... .
Be structured: Time block your work. ... .
Be self-aware: Track your time..

What are the 4 key stages of effective time management?

Four Steps to Project Time Management.
Define the Activities..
Sequence the Activities..
Estimate Activity Resources..
Develop and Control the Schedule..

What are the 4 types of time management?

The 4 Ds are: Do, Defer (Delay), Delegate, and Delete (Drop). Placing a task or project into one of these categories helps you manage your limited time more effectively and stay focused on what matters most to you.

What are the stages of time management?

The four stages of time management focus on distinctive aspects of the way all of us use our time..
Idea Creation. “Passion is energy. ... .
Strategy. The biggest risk is not taking any risk… ... .
Process. ... .
Reflection..